Project Description

68

TURBINES

200 m

TOTAL HEIGHT

183 MW

INSTALLED EFFECT

– TWH

ANNUAL ESTIMATED PRODUCTION

Ersträsk is the second sub-project of Phase 1 of Markbygden 1101, located at the north-western area of Phase 1. The sub-project received all permits to erect and operate up to 77 wind turbines, however updated plans of the investor only considering 68 wind turbines of which 26 turbines were commissioned in 2018. All turbines will be connected via an overhead-line to the Råbäcken substation, owned by Markbygden Net AB, and then further to Svenska Kraftnät’s 400kV grid.

Transferred: This project has been transferred to a third party in 2015.

All figures and values (above) relating to the number of turbines, outputrated power, and estimated production are preliminary and may change during the project’s completion.