Road construction at Ersträsk

ERSTRÄSK

ERSTRÄSK

77 
Turbines
200 m
Total Height
183 MW
Rated Power

* All numbers are estimates that may change in the future as the project progresses towards completion.

Ersträsk wind farm is the second construction stage of Phase 1, located in its western part. Ersträsk potentially will consist of 77 turbines. Tree cutting and road constructions began in 2013. The wind farm will be connected, once commissioned, to the substation Råbäcken owned by Markbygden Net AB and further to the Svenska Kraftnät 400kV grid. 

Vended: This project has been sold to a third party for further exploitation.

Photos

Photos of Ersträsk. Click on a photo to enlarge it.

Road construction at Ersträsk

Road construction at Ersträsk

22 May 2013 10:29

View from Ersträsk

View from Ersträsk

20 March 2013 10:30